Product: asset lifecycle
Every addition, transfer, disposal and project is a dated event.
A register is a history. Because the events are dated, the roll-forward reconciles and any prior period can be reproduced.
| Asset | Description | From location | To location | From GL | To GL | Portion |
|---|---|---|---|---|---|---|
| 10412 | Vertical machining center | Plant 1 / Cell 4 | Plant 2 / Cell 1 | 1540-100 | 1540-200 | 100% |
| 10603 | Warehouse racking, aisle 3 | Warehouse | Plant 2 | 1570-300 | 1570-200 | 100% |
| 10120 | Nonresidential improvement, Bldg 2 | Plant 1 | Plant 1 (50%), Plant 2 (50%) | 1520-100 | 1520-100 / 1520-200 | 50% split |
Eight kinds of event, and what each produces.
| Event | What is recorded | What it produces |
|---|---|---|
| Addition | Cost, in-service date, class, location, GL accounts, four books' settings | First-year depreciation in each book; additions report; GL journal |
| Construction in progress | Project costs by invoice | Capitalisation into one or many assets |
| Transfer, whole or partial | From and to, effective date, share | Expense split at the date; transfer report |
| Disposal, whole or partial | Date, proceeds, expenses of sale, share | Gain or loss by book; Section 1245 and 1250 recapture; GL journal |
| Revaluation or impairment | New basis or remaining life, reason | Logged override; recalculated from the date |
| Lease | Lessor, term, payments | Right-of-use asset and schedule |
| Split and component | Components with their own lives | Depreciate separately, report under the parent |
| Physical count | Scanner results by location | Not-found and wrong-location exceptions |
Construction in progress becomes an asset in one step.
| Project | Description | Location | Budget | Cost to date | Committed | Spent | In service | Status |
|---|---|---|---|---|---|---|---|---|
| CIP-0148 | Line 2 conveyor upgrade | Plant 2 | 120,000.00 | 86,410.00 | 21,300.00 | 72% | Nov 2026 | In progress |
| CIP-0151 | Plant 2 roof replacement | Plant 2 | 210,000.00 | 164,850.00 | 40,000.00 | 78% | Dec 2026 | In progress |
| CIP-0153 | Wastewater SCADA upgrade | Plant 1 | 95,000.00 | 71,200.00 | 0.00 | 75% | Oct 2026 | In progress |
| CIP-0155 | Warehouse dock doors (4) | Warehouse | 48,000.00 | 48,000.00 | 0.00 | 100% | Ready | Ready to capitalise |
| CIP-0157 | HQ standby generator | HQ | 118,000.00 | 115,950.00 | 0.00 | 98% | Ready | Ready to capitalise |
| Total cost to date, all projects | 486,410.00 | 61,300.00 | ||||||
A disposal is computed in every book before it is recorded.
| Schedule | Cost | Accumulated to date | NBV | Gain or (loss) | Recapture |
|---|---|---|---|---|---|
| Book | 58,900.00 | 23,560.00 | 35,340.00 | (13,690.00) | |
| Federal | 58,900.00 | 49,481.68 | 9,418.32 | 12,231.68 | Section 1245, 12,231.68 |
| State | 58,900.00 | 30,628.00 | 28,272.00 | (6,622.00) | |
| AMT | 58,900.00 | 41,230.00 | 17,670.00 | 3,980.00 | Section 1245, 3,980.00 |
| Line | Cost | Accumulated depreciation | Net book value |
|---|---|---|---|
| Beginning balance, 1 Jan 2026 | 4,812,340.00 | (2,106,918.25) | 2,705,421.75 |
| Additions | 386,700.00 | 386,700.00 | |
| Transfers in from CIP | 142,000.00 | 142,000.00 | |
| Disposals | (91,250.00) | 88,430.10 | (2,819.90) |
| Depreciation expense | (512,884.60) | (512,884.60) | |
| Ending balance, 31 Dec 2026 | 5,249,790.00 | (2,531,372.75) | 2,718,417.25 |
The roll-forward reconciles because the events are dated.
Named users with roles (view, enter, approve, close). Additions wait in a queue until approved. Closed periods lock.
The questions asked about events and closed periods, answered.
Can an asset be partly disposed of or partly transferred?
Yes. A partial disposal takes a share of cost and accumulated depreciation in every book and computes gain, loss and recapture on that share; a partial transfer splits cost and expense from the effective date.
What happens to a closed period if we find an error?
Closed periods are locked; the correction is an adjustment in the current period with a note, and the audit trail shows what changed.
How do additions get into the register?
From the A/P export into a review queue, from an Excel or CSV file with a saved map, or by entry. Nothing depreciates until an approver posts it.
Does it do a physical inventory?
Yes. Print barcode labels, count with a scanner, load the file; the exceptions report lists what was not found, misplaced, or found but not on the register.
Try it on your own register.
Fourteen days, the full product, no card. Load your assets, run a schedule, compare it with what you filed.
Start the 14-day trialRequest a demo
Hosted by us in a dedicated environment for your organisation, or on your own server. One database per customer; your data is exportable in full at any time.
Priced by asset records. Every plan is the full product. Your data is exportable in full, at any time, at no charge. Plans from $1,000 a year.